Confirm Equipment Requirements Before Shipment
Before the equipment leaves the warehouse, establish how it will enter the booth, turn into position, connect to services, operate, and be tested. These decisions should come from ProMat material handling equipment display planning, where dimensions, attachments, service clearance, visitor access, and operating needs are defined.
Equipment Move-In Sequence
This sequence sets the working order for crate delivery, flooring, booth construction, equipment placement, utility connections, screens, and graphics.
Service Clearance
Keep enough open space around or behind the equipment for connections, operation, inspection, maintenance, and staff access after placement.
Functional Testing
This is the point where the equipment, controls, utilities, screens, and complete demonstration cycle are tested together before the booth opens.
Before shipment, verify:
Equipment dimensions, weight, and crate size
Attachments, turning requirements, and final orientation
Power, controls, and planned connection locations
Service clearance and staff access
Testing method and reset procedure
Unresolved details at this stage can delay move-in or force late changes to utilities, graphics, and the surrounding booth structure.

Freight arrival, staging, flooring, and forklift access should be coordinated before heavy equipment enters the booth and moves into its final position.
Static Displays and Operating Equipment Need Different Access
A static equipment display mainly depends on stable placement, readable graphics, and clear visitor and service access. An operating equipment demonstration adds power, movement, operator access, repeated testing, and recovery planning, so it usually needs to remain accessible longer during setup.
Static Equipment Display
Verify the footprint, weight, and final orientation
Keep viewing and service access clear
Secure attachments, samples, and loose components
Align specification graphics with the equipment
Complete stability and placement checks
Operating Equipment Demonstration
Establish the movement range and safety clearance
Confirm equipment booth power, control, and utility requirements
Keep operator and maintenance access open
Repeat equipment demo testing under expected show conditions
Rehearse the reset and failure-recovery process
A static display can usually be released once placement and stability are verified. Operating equipment should remain accessible until power, movement, controls, safety, and the full demo cycle have been tested together.

Static displays focus on stable placement and readable graphics, while operating equipment also needs power, safety clearance, operator access, and repeated demo testing.
Conveyor and Powered Equipment Create Different Bottlenecks
Different equipment types restrict the work area in different ways. A conveyor section mainly affects access and assembly routes. Powered equipment also introduces turning, charging, cable, service, and testing requirements.
Conveyor Equipment Arrival
A conveyor section that reaches the floor before the flooring and main structure are complete can close the installation route and require a second move. Preparing the work area first allows the section to enter once, follow the planned path, and move directly into its final position.
Powered Equipment Arrival
Powered equipment needs more than its display footprint. Turning space, placement support, charging access, cable routes, service clearance, and functional testing all affect when it can enter and where it can remain.
An early arrival may block construction or utility work. A late arrival can create the opposite problem: walls, counters, or graphics may leave too little room for safe positioning and testing.
Coordinate Freight, Flooring, and Structure in One Sequence
Heavy equipment setup depends on shared access. Freight, flooring, booth construction, equipment placement, utilities, and graphics often use the same work area, so one early delivery can interrupt several later tasks. A large crate may prevent flooring work, restrict wall assembly, or close the route needed for a forklift and final placement.
Complete the flooring and any primary structure that will not reduce equipment access first. Large equipment should move into position before remaining walls, counters, or displays narrow the route. Forklift and placement support should arrive while the path is still open and the floor is protected.
Large wall graphics may need to be installed before equipment placement. Specification panels and equipment-specific graphics can usually wait until the final orientation is known.
Stage | Main Requirement | Confirm Before Moving On |
|---|---|---|
Before shipment | Equipment data | Dimensions, weight, crate size, attachments, utility requirements, and planned connection locations |
Freight arrival and staging | Access and handling | Delivery timing, staging space, forklift access, and handling method |
Flooring and primary structure | Protected work area | Flooring, load requirements, supports, and an open placement route |
Equipment placement | Final position | Orientation, service clearance, visitor access, and operator access |
Utility connection | Power and controls | Final connection points, cable paths, controls, and network services |
Functional testing | Repeatable operation | Start, stop, full demo cycle, reset, and failure recovery |
Final inspection | Show readiness | Visitor path, packaging removal, tools, cables, graphics, and safety conditions |
This sequence is usually mapped during freight and pre-show logistics coordination, when delivery timing, staging, equipment handling, and booth construction can be reviewed together.

Power, controls, network services, and cable routes should be finalized only after the equipment position, service clearance, and visitor path are confirmed.
Final Position First, Connections and Testing Second
Equipment should be positioned, leveled, and checked in its final orientation before power, controls, network lines, and other utility connections are finalized. Connection points and cable routes should match the actual equipment position, remain clear of visitor and service paths, and leave controls and emergency-stop access within reach.
Before walls, graphics, or attachments reduce the working area, verify that service clearance remains open on every side needed for operation, maintenance, or reset access.
Full equipment demo testing should begin only after the equipment will no longer be moved. Even a small adjustment can affect cable lengths, safety clearance, screen sightlines, and the demo reset route.
Once the equipment reaches the booth, equipment placement and on-site installation need to stay on the same schedule.
Final Booth Checks at McCormick Place
Late-stage problems are harder to correct once the equipment is positioned and the remaining work area is limited. Before releasing the booth, review both the setup decisions and the final visitor-facing condition.
Common Mistakes
Crate dimensions and handling needs were not verified
Walls or attachments reduced service clearance
Power, controls, or cable paths were approved too late
Testing and failure recovery were left until the final labor window
Tools, cables, and packaging remained in visitor areas
Final Inspection
Check:
Final equipment position and operating state
Service clearance and staff access
Power, controls, screens, and labels
Floor protection and visitor paths
Removal of tools, cables, crates, and packaging
ProMat Equipment Setup FAQ
When should equipment arrive for a ProMat booth?
Equipment should arrive only after the flooring and primary structure are ready and the access route is clear. Forklift availability, staging space, crate handling, and the delivery window should also be verified before move-in begins.
What should be ready before equipment placement?
The flooring, main structure, placement route, utility locations, and final equipment orientation should be established first. Service clearance and staff access must also remain open after the equipment reaches its final position.
When should power and functional testing begin?
Power connections and functional testing should begin after final positioning is complete and the equipment will no longer be moved. Controls, cables, and service points must remain accessible, with the full operating cycle tested before cleanup and final inspection.